# OpenLab power and failsafe checklist

Version/configuration: ______  Date: ______  Venue: ______  Adult stop operator: ______

This record is blank by design. Completing it requires the exact approved hardware and local procedure.

## Isolated preflight

- [ ] BOM, schematic, pin table, firmware hash, and physical assembly revisions agree.
- [ ] No damaged or quarantined part is installed.
- [ ] Ratings and measured/documented motor stall demand were reviewed.
- [ ] Polarity, continuity, insulation, strain relief, guards, fasteners, and isolation checked.
- [ ] Power source/protection is approved; no mains work or unprotected battery.
- [ ] Driver enable defaults to disabled during reset/boot.
- [ ] Test barrier and clear exclusion area in place.

Reviewer/signature under host procedure: ______

## Controlled test

| Test | Expected | Observed | PASS/FAIL/NOT RUN | Evidence ref |
|---|---|---|---|---|
| Manual motor isolation | motor energy removed | | | |
| Software disabled | zero wheel targets | | | |
| Watchdog timeout | zero wheel targets | | | |
| Invalid sensor input | zero wheel targets | | | |
| Reset/boot | driver remains disabled | | | |
| Left low command | correct direction/current | | | |
| Right low command | correct direction/current | | | |
| Fault/stop recovery | requires deliberate re-enable | | | |

Any failure pauses operation. Record the fault, isolate the system, quarantine parts where relevant, and obtain documented mitigation approval before retest.